India contracted green ammonia from Rs 49.75 a kg, and the supply start dates are not public

T
Tejvir Singh
3 min read
3 min read
India contracted green ammonia from Rs 49.75 a kg, and the supply start dates are not public

A fertiliser, refinery or chemicals company left out of India's first green ammonia round now has to decide whether to commit to green ammonia or hydrogen offtake in the next tender, or wait for the first plants to deliver. The first round set low prices, and its supply start dates have not been published.

The Solar Energy Corporation of India ran the auctions under the SIGHT scheme. JMK Research reported in August 2025 that ACME won 100,000 tonnes a year for IFFCO's Paradeep plant at Rs 49.75 per kg, which it put at 10.1% above grey ammonia at US$515 a tonne. Mercom reported on 31 March 2026 that SECI had signed six agreements for 670,000 tonnes a year out of 724,000 allocated, for 10 years, at tariffs from Rs 49.75 to Rs 64.74 per kg.

The price is fixed and the start date is private. Ammonia Energy Association, writing on 14 April 2026, said each agreement carries a Scheduled Commencement of Green Ammonia Supply Date, the agreements have not been published, and the subsidy covers the first three years of each ten-year contract. The IEA's Global Hydrogen Review 2026 credits SECI and refinery tenders with producing offtake contracts, and adds that whether all the deals move forward depends on government incentives whose availability is still unclear.

Europe pays far more. Mercom put the international price at about EUR 1,000 a tonne, roughly Rs 110 per kg, and Germany's H2Global pilot awarded Fertiglobe's Egyptian project a delivered price of EUR 1,153 per tonne of renewable ammonia, for at least 40,000 tonnes a year between 2028 and 2033, Ammonia Energy Association reported. Worldwide the pipeline is shrinking. The IEA says committed projects and those with strong potential to run by 2030 fell from 10 million tonnes of hydrogen a year in its previous review to just above 6 million tonnes, and that 22 million tonnes of announced capacity may lose any chance of operating by 2030 without investment decisions by early 2027.

Our judgment is that fewer than half of the 724,000 tonnes a year allocated will be delivered in the year to 31 March 2029, because the projects still need financing and their start dates are not public. We are wrong if SECI or the renewable energy ministry reports more than 362,000 tonnes supplied in that year.

We would bid in the next round only if the contract publishes a supply start date and pays compensation for each month of delay, and we would keep the grey ammonia contract running until the first green cargo arrives. A Rs 49.75 price helps a buyer only once the ammonia is delivered.

Sources (5)
  1. JMK Research, Green ammonia is only 10% costlier than grey in the latest SIGHT Mode 2A auctions (27 August 2025)
  2. Mercom India, SECI signs deals for supply of 670,000 TPA green ammonia to fertilizer units (31 March 2026)
  3. Ammonia Energy Association, Purchase agreements signed with Indian renewable ammonia auction winners (14 April 2026)
  4. Ammonia Energy Association, Renewable ammonia price discoveries: a closer look at the H2Global and SECI auctions (6 August 2025)
  5. IEA, Global Hydrogen Review 2026, Executive summary